Section title: Requests for Interpretation
RFI #
1205
835 Service Date
Description

Service date in loop 2110 can represent either single date (DTP01 = 472) or a period (DTP01 = 150 and 151).Is it Ok to send just one date Period Start (150) or Period End (151)? Or if one is sent the other one is required ?

RFI Response

If the service date is one day –the service took place on only one day and did not span multiple days, then you would use 472 with one date.If the service spanned multiple dates you would put in 150 as the first day and 151 as the last day of the span of dates. If you are using 150 then you MUST use 151.

DOCUMENT ID
005010X221